September 20

Ongoing / Upcoming Scheduled Work (September 23, 2019thru October 7, 2019 ):

  • Work hours are Monday thru Friday, 7:00 AM to 7:30 PM – Gates closing at 8:00 PM. Advance notice will be given prior to weekend work.

  • Continue forming, reinforcing and placing walls, columns and slabs.

  • Continue installation of plumbing and electrical work in deck slabs.

  • Continue installation of site utilities in easement. Access for West End Place residents and deliveries

    will be continuously maintained.

Work with Potential for Noise Impacts

  • Concrete deliveries.

  • Pumping of concrete.

  • Air horn used to notify workers of overhead crane picks.

  • Saw cutting of rebar.

  • Jackhammering

Roadway and Sidewalk Impairment

  • Periodic small deliveries along Thoreau Path to access the tennis courts.

  • West End Place Driveway – Utilizing lane within barricaded fence for utility installation, concrete and rebar deliveries. Access for West End Place residents and deliveries will be continuously maintained.

  • A vacuum truck will periodically be on Thoreau Path to access and vacuum the frac tank.

  • Dumpster deliveries and pickups will access the site via Thoreau Path.

  • Concrete, rebar and miscellaneous deliveries via Lomasney Way.

What is that...

  • Truck that is parked at the front of the site that has a long arm (boom) with a hose at the end? This is the concrete pump truck which is used to pump high volumes of concrete in hard to reach areas.

Weekend Work & Holiday Work

Saturday Work projected

  • We will be working Saturday, September 21st, 2019, to perform concrete activities.

  • We anticipate working Saturday, September 28th, 2019, to perform concrete activities.

Sunday Work projected – No Work Anticipated

Holiday Work – No Work anticipated

Off Hours 

  • Pease note that a security guard is on site Monday to Saturday from 6:00 PM to 6:00 AM, and Sunday from 6:00 AM to Monday morning at 6:00 AM patrolling the site. Also, a security guard will be on site on holidays.

Upcoming Meetings

  • A Tishman Construction representative will attend the Amy Lowell coffee hour on Thursday, 9/26/19 at 1:00 PM.

Current Sub-Contractors On-Site

  • J. Derenzo Company (Sitework)

  • Waltham Pest Control (Pest Control)

  • Sullivan & McLaughlin (Electrician)

  • S&F Concrete (Concrete)

  • JC Cannistraro (Plumbing)

  • Heritage Restoration (Waterproofing)

  • Simplex Grinnell (Fire Protection)

  • Lund Steel (Reinforcing Steel)

  • Andy Frain Services (Security)

Tishman Construction Neighborhood Liaison

Barry McGrath Barry.mcgrath@aecom.com